A/A
|
Critical Questions
|
Yes
|
No
|
N/A
|
Development of Activities Schedule
|
|
|
|
1.
|
Have the major project deliverables been subdivided into smaller more manageable components?
|
|
|
|
2.
|
Have the activities needed to produce the project deliverables been identified?
|
|
|
|
3.
|
Have the activities’ sequence, dependencies and constraints been determined?
|
|
|
|
4.
|
Has the duration of each activity/ task been estimated?
|
|
|
|
5.
|
Have the start up and completion dates of each activity/ task been defined?
|
|
|
|
6.
|
Has the baseline Activities Schedule been developed?
|
|
|
|
7.
|
Has the critical path been identified?
|
|
|
|
Development of Resource Plan
|
|
|
|
8.
|
Have the types of the resources required in order to perform project activities and tasks been identified and quantified?
|
|
|
|
9.
|
Have the exact time and the duration that each resource will be utilised, been estimated?
|
|
|
|
10.
|
Has the baseline Resource Schedule been developed?
|
|
|
|
11.
|
Have the resources been assigned to specific activities/ tasks of the project?
|
|
|
|
Development of Cost Plan
|
|
|
|
12.
|
Have all the types of costs expected to be incurred in the project been identified?
|
|
|
|
13.
|
Have the costs expected to be incurred been estimated?
|
|
|
|
14.
|
Is there an estimation on when each cost is expected to be incurred?
|
|
|
|
15.
|
Has the baseline cost schedule been developed?
|
|
|
|
16.
|
Has the cost of undertaking each activity/ task laid down in the Activities Schedule been estimated?
|
|
|
|
Development of Quality Plan
|
|
|
|
17.
|
Have the quality targets to be achieved by each deliverable been defined?
|
|
|
|
18.
|
Have the quality assurance and quality control processes to be employed during the implementation of the project been established?
|
|
|
|
19.
|
Have quality assurance roles been assigned to project team members?
|
|
|
|
20.
|
Has the Quality Plan been compiled?
|
|
|
|
Development of Issue Management Plan
|
|
|
|
21.
|
Has the process to be used for issue management been defined?
|
|
|
|
22.
|
Have the documents to be used for raising and registering an issue been designed?
|
|
|
|
23.
|
Have the roles and responsibilities that will be involved in the issue management process been defined?
|
|
|
|
Development of Change Management Plan
|
|
|
|
24.
|
Has the process to be used for change management been defined?
|
|
|
|
25.
|
Has the form to be used for requesting a change been designed?
|
|
|
|
26.
|
Have the roles and responsibilities that will be involved in the change management process been defined?
|
|
|
|
Development of Risk Plan
|
|
|
|
27.
|
Have potential risks affecting the project been identified?
|
|
|
|
28.
|
Have the characteristics of the identified risks been documented in the Risks Log?
|
|
|
|
29.
|
Have the identified risks been evaluated in terms of the likelihood of their occurrence and the magnitude of their impact?
|
|
|
|
30.
|
Have preventive and contingency actions for each possible risk been defined?
|
|
|
|
31.
|
Has the process to be used for risk management been defined?
|
|
|
|
32.
|
Have the responsibilities of risk identification, evaluation and mitigation been assigned to project team members?
|
|
|
|
Development of Acceptance Plan
|
|
|
|
33.
|
Have the criteria and standards for the acceptance of the project deliverables been established?
|
|
|
|
34.
|
Has the process of performing acceptance tests been defined and documented?
|
|
|
|
35.
|
Has the responsibility of performing the acceptance tests been assigned to certain project team members?
|
|
|
|
Establishing Performance Indicators
|
|
|
|
36.
|
Have performance indicators been established for evaluating the progress and the achieved benefits of the project?
|
|
|
|
37.
|
Has the process for measuring performance indicators been defined?
|
|
|
|
Development of Communication Plan
|
|
|
|
38.
|
Have the stakeholders requiring regular information about the project been identified?
|
|
|
|
39.
|
Have the communication needs of the identified stakeholders been determined?
|
|
|
|
40.
|
Has the Communication strategy been developed?
|
|
|
|
41.
|
Has the Communication Plan/ matrix been completed?
|
|
|
|
42.
|
Have the Performance Reporting procedures (i.e. Progress & Status Reporting) been planned?
|
|
|
|